Construction of Timber Frame Additions 

A timber frame addition is one of those showstopping home upgrades, but it requires a significant investment, both in terms of time and resources. Whether you’re dreaming of a sun-drenched great room, a rustic kitchen extension, or a timber-framed entrance, you should first get familiar with the overall project scope and what to expect at each stage.  

Below, we break down the process and how long it takes for each milestone.  

Stage 1: Planning & Design (4–8 weeks) 

Timeframe: 1–2 months 
Key Players: Homeowner, designer, engineer, builder 

What Happens: 

  • Initial Consultation: Discuss your goals, timeline, and budget with a timber frame specialist. 
  • Site Evaluation: A builder visits your home to assess the structural and spatial possibilities. 
  • Preliminary Designs: Concept drawings and 3D renderings help you visualize the addition. 
  • Engineering Review: Structural elements are assessed to ensure compliance with building codes. 

Stage 2: Permitting & Approvals (4–12 weeks) 

Timeframe: 1–3 months 
Key Players: Builder, architect/designer, local building authority 

What Happens: 

  • Permit Drawings: Your designer finalizes architectural and structural drawings for submission. 
  • Permit Submission: Application is submitted to the local municipality for approval. 
  • Zoning & Code Review: The city checks that your addition complies with bylaws and building codes. 
  • Permit Issuance: Once approved, you can legally start construction. 

Some municipalities are faster than others. Urban areas may take longer due to high volume. 

Stage 3: Site Preparation & Logistics (1–3 weeks) 

Timeframe: 1–3 weeks 
Key Players: Homeowner, general contractor 

What Happens: 

  • Utility Relocation: Electrical, plumbing, HVAC may need adjustment. 
  • Interior Prep: Rooms near the addition area may need to be cleared or sealed off. 
  • Temporary Living Adjustments: Depending on the room, you may need to move out temporarily (e.g., kitchen or master suite additions). 

Stage 4: Timber Frame Fabrication (4–10 weeks – concurrent with permitting) 

Timeframe: Often overlaps with permitting 
Key Players: Timber frame contractor 

What Happens: 

  • Frame Engineering: Final measurements and design details are sent to the fabricator. 
  • Cut & Prep: Timber is cut, joined, and prepped in a workshop. 
  • Delivery Scheduling: Once the frame is ready, delivery is scheduled to align with a ready site. 

Stage 5: Foundation & Framing (3–6 weeks) 

Timeframe: 1–1.5 months 
Key Players: Builder, subcontractors 

What Happens: 

  • Foundation Installation: Excavation, concrete pour, and curing. 
  • Frame Erection: Timber frame is delivered and raised on-site. 
  • Roofing & Sheathing: Once the frame is up, it’s quickly enclosed to protect it from the elements. 

This is one of the most exciting stages. Raising day is often a major milestone. 

Stage 6: Enclosure & Exterior Work (2–4 weeks) 

Timeframe: 2–4 weeks 
Key Players: Builder, siding and window contractors 

What Happens: 

  • Doors & Windows Installed 
  • Roof Finished 
  • Weatherproofing Completed 

Stage 7: Interior Finishing (4–10 weeks) 

Timeframe: 1–2.5 months 
Key Players: Electricians, plumbers, drywallers, finish carpenters, painters 

What Happens: 

  • Rough-ins: Electrical, HVAC, and plumbing installed. 
  • Insulation & Drywall: Walls are sealed and prepared for paint. 
  • Flooring, Trim, Fixtures: Finishing touches are installed. 

This is the stage with the most variability. Custom interior finishes and supply delays can extend timelines. 

Stage 8: Final Inspection & Move-In (1 week) 

Timeframe: 1 week or less 
Key Players: Builder, municipal inspector 

What Happens: 

  • Building Inspection: City inspector ensures everything complies with your permit. 
  • Deficiency Review: Your contractor walks you through final details. 
  • Move-In: Enjoy your new timber-framed space! 

Total Timeline Summary 

Stage Duration 
Planning & Design 4–8 weeks 
Permitting 4–12 weeks 
Timber Frame Fabrication 4–10 weeks (parallel) 
Site Prep 1–3 weeks 
Foundation & Framing 3–6 weeks 
Enclosure & Exterior Finishes 2–4 weeks 
Interior Finishes 4–10 weeks 
Final Inspections ~1 week 
Total 4–7 months 

Relocation Tips Based on Room 

Room Involved What to Plan For 
Kitchen Addition Relocate cooking setup, store perishables 
Bedroom Addition Temporary sleeping arrangement needed 
Bathroom Addition Plan alternate access or schedule sharing 
Living Room Consider a seasonal renovation (use patio) 
Entryway Set up back, side or patio doors as main entry 

Ready to Start Your Timber Frame Addition? 

Tucker Homes designs and builds timber frame additions with clear plans, steady timelines and quality you can count on. 

Book a consultation today to start planning your timber frame transformation.